In the last two hundred years there have been great changes in the method of production of goods. This is now also true of the building industry; for mechanization has been introduced. System building can save both time and money. The principle of system building is that the building is made from a set of
standard units. These are either made at the building-site or at a factory. Some designers, in fact, are standardizing the dimensions of rooms. They are made in multiples of a single fixed length, usually ten centimeters. This is called a modular system, and it means that manufactures can produce standardized fittings at a lower cost. The most important fact about system building is its speed. A ten-storey flat, for example, can be completed in four months.
There are several new methods of system building. One is the panel method. In this case, the construction company sometimes erects a factory on the site. The walls and floors of the building, called panels, are cast in a horizontal or vertical position. Conduits for electrical wires and sleeves for pipes are cast in the panels when they are being made. The moulds for making these castings are situated all around the building.
After the concrete panels are cast, they are allowed to set and harden for a week. Next they are lifted by a tower crane on to any section of the building. There the panels are cemented together at their joints and the floor covering is laid.
After the panels have been cemented together, the crane lifts a case into the area. It contains all the fittings to be installed, such as wash-basins, radiators and pipes. Finishing tradesmen, such as plumbers, plasterers, painters and electricians, follow behind to complete the work.
In some building developments, in some countries, whole flats with internal features like their bathrooms, bedrooms and connecting stairs, and weighing as much as twenty tons, are carried to the building-site ready-made. A giant overhead crane is used to lift them into position. In the future, this method may become more widespread.
1. The main difference between panel method and the method discussed in the last paragraph is_______.
A. the latter uses ready-made internal features
B. panels are cast in a level position
C. the former is used to build walls and floors while the latter to construct bathrooms or bedrooms
D. the former is more expensive than the latter
22. Which of these statements is TRUE of system building?
A. It employs more men. B. It is difficult and dangerous.
C. It can save both time and money. D. It means less mechanization.
23. According to the passage, the principle of system building is that_______.
A. construction methods are safer
B. buildings are made from a set of standardized units
C. similar buildings can be produced
D. all units are produced on the site
24. The usual fixed length in the modular system is_______.
A. twenty centimeters B. ten millimeters
C. fifty centimeters D. ten centimeters
25. What lifts the concrete panels onto the building?
A. Cranes. B. Man-power.
C. Pulleys. D. Hydraulic jacks.
21. A 22. C 23. B 24. D 25. A
考研英语词汇统计19
考研妙招:根据题型记考研英语词汇更有效
考研英语辅导:词汇自我测试第一天
考研英语词汇统计23
考研英语近义词辨析及举例三
考研英语:暑期备考 单词不能少
考研辅导之用句型背单词十四
考研辅导之用句型背单词四十九
考研辅导之用句型背单词十二
考研英语词汇统计15
考研英语:常用词汇辨析
考研辅导之用句型背单词二十五
考研辅导之用句型背单词十
考研英语词汇统计17
考研英语词汇统计13
考研辅导之用句型背单词二十七
考研辅导之用句型背单词六
考研辅导之用句型背单词十一
考研辅导之用句型背单词二
考研英语词汇统计25
考研辅导之用句型背单词五十三
考研辅导之用句型背单词三十五
考研辅导之用句型背单词五十二
考研英语词汇统计20
考研通关经验分享:考研英语词汇背诵技巧
考研英语近义词辨析及举例二
考研英语词汇统计21
考研英语词汇统计6
考研辅导之用句型背单词十三
考研辅导之用句型背单词五
不限 |
英语教案 |
英语课件 |
英语试题 |
不限 |
不限 |
上册 |
下册 |
不限 |