In the last two hundred years there have been great changes in the method of production of goods. This is now also true of the building industry; for mechanization has been introduced. System building can save both time and money. The principle of system building is that the building is made from a set of standard units. These are either made at the building-site or at a factory. Some designers, in fact, are standardizing the dimensions of rooms. They are made in multiples of a single fixed length, usually ten centimeters. This is called a modular system, and it means that manufactures can produce standardized fittings at a lower cost. The most important fact about system building is its speed. A ten-storey flat, for example, can be completed in four months.
There are several new methods of system building. One is the panel method. In this case, the construction company sometimes erects a factory on the site. The walls and floors of the building, called panels, are cast in a horizontal or vertical position. Conduits for electrical wires and sleeves for pipes are cast in the panels when they are being made. The moulds for making these castings are situated all around the building.
After the concrete panels are cast, they are allowed to set and harden for a week. Next they are lifted by a tower crane on to any section of the building. There the panels are cemented together at their joints and the floor covering is laid.
After the panels have been cemented together, the crane lifts a case into the area. It contains all the fittings to be installed, such as wash-basins, radiators and pipes. Finishing tradesmen, such as plumbers, plasterers, painters and electricians, follow behind to complete the work.
In some building developments, in some countries, whole flats with internal features like their bathrooms, bedrooms and connecting stairs, and weighing as much as twenty tons, are carried to the building-site ready-made. A giant overhead crane is used to lift them into position. In the future, this method may become more widespread.
1. The main difference between panel method and the method discussed in the last paragraph is
A. the latter uses ready-made internal features
B. panels are cast in a level position
C. the former is used to build walls and floors while the latter to construct bathrooms or bedrooms
D. the former is more expensive than the latter
2. Which of these statements is TRUE of system building?
A. It employs more men. B. It is difficult and dangerous.
C. It can save both time and money. D. It means less mechanization.
3. According to the passage, the principle of system building is that
A. construction methods are safer
B. buildings are made from a set of standardized units
C. similar buildings can be produced
D. all units are produced on the site
4. The usual fixed length in the modular system is
A. twenty centimeters B. ten millimeters
C. fifty centimeters D. ten centimeters
5. What lifts the concrete panels onto the building?
A. Cranes. B. Man-power.
C. Pulleys. D. Hydraulic jacks.
参考答案: 1. A 2. C 3. B 4. D 5. A
新版gre写作新题库:argument68
新版gre作文新题库解析-issue97
新版gre作文新题库解析-issue92
新版gre写作新题库:argument66
新版gre写作新题库:argument65
新版gre作文新题库解析-issue75
新版gre作文新题库解析-issue60
新版gre作文新题库解析-issue93
新版gre作文新题库解析-issue99
新版gre写作新题库:argument72
新版gre写作新题库:argument73
新版gre作文新题库解析-issue100
新版gre作文新题库解析-issue94
新版gre作文新题库解析-issue105
新版gre作文新题库解析-issue81
新版gre写作新题库:argument71
新版gre写作新题库:argument58
新版gre写作新题库:argument63
新版gre作文新题库解析-issue76
新版gre作文新题库解析-issue83
新版gre作文新题库解析-issue84
新版gre作文新题库解析-issue96
新版gre作文新题库解析-issue107
新版gre作文新题库解析-issue66
新版gre写作新题库:argument74
新版gre作文新题库解析-issue73
新版gre写作新题库:argument69
新版gre作文新题库解析-issue95
新版gre写作新题库:argument101
新版gre作文新题库解析-issue90
不限 |
英语教案 |
英语课件 |
英语试题 |
不限 |
不限 |
上册 |
下册 |
不限 |