In the early days of nuclear power, the United States make money on it. But today opponents have so complicated its development that no nuclear plants have been ordered or built here in 12 years.
The greatest fear of nuclear power opponents has always been a reactor meltdown. Today, the chances of a meltdown that would threaten U. S. public health are very little. But to even further reduce the possibility, engineers are testing new reactors that rely not on human judgment to shut them down but on the laws of nature. Now General Electric is already building two advanced reactors in Japan. But dont expect them even on U. S. shores unless things change in Washington.
The procedure for licensing nuclear power plants is a bad dream. Any time during, or even after, construction, an objection by any group or individual can bring everything to a halt while the matter is investigated or taken to court. Meanwhile, the builder must add nice-but-not-necessary improvements, some of which force him to knock down walls and start over. In every case when a plant has been opposed, the Nuclear Regulation Commission has ultimately granted a license to construct or operate. But the victory often costs so much that the utility ends up abandoning the plant anyway.
A case in point is the Shoreham plant on New Yorks Long Island. Shoreham was a virtual twin to the Millstone plant in Connecticut, both ordered in the mid-60s. Millstone, completed for $ 101 million, has been generating electricity for two decades. Shoreham, however, was singled out by antinuclear activists who, by sending in endless protests, drove the cost over $ 5 billion and delayed its use for many years.
Shoreham finally won its operation license. But the plant has never produced a watt power. Governor Mario Cuomo, an opponent of a Shoreham start up, used his power to force New Yorks public-utilities commission to accept the following settlement: the power company could pass the cost of Shoreham along to its consumers only if it agreed not to operate the plant. Ioday, a perfectly good facility, capable of servicing hundreds of thousands of homes, sits rusting.
21.The authors attitude toward the development of nuclear power is______.
A. negative B. neutral
C. positive D. questioning来自www.Examw.com
22.What has made the procedure for licensing nuclear power plants a bad dream?
A. The inefficiency of the Nuclear Regulation Commission. B. The enormous cost of construction and operation.
C. The length of time it takes to make investigations.
D. The objection of the opponents of nuclear power.
23.It can be inferred from Paragraph 2 that______.
A. there are not enough safety measures in the U. S. for running new nuclear power plants
B. it is not technical difficulties that prevent the building of nuclear power plants in the U. S.
C. there are already more nuclear power plants than necessary in the U. S.
D. the American government will not allow Japanese nuclear reactors to be installed in the U. S.
24. Governor Mario Cuomos chief intention in proposing the settlement was to_______.
A. stop the Shoreham plant from going into operation
B. urge the power company to further increase its power supply
C. permit the Shoreham plant to operate under certain conditions
D. help the power company to solve its financial problems
25. The phrase single out is closest in meaning to_______.
A. delay B. end up
C. complete D. separate
参考答案:21. C 22. D 23. B 24. A 25. D
大学英语四级提高听力必知的方法与技巧
四级听力不给力的4大原因
大学英语四级复合式听写技巧
英语四级听力复合式听写真题
大学英语四级短对话听力技巧
大学英语四级考试答案解析
英语四级听力短对话同义替换(4)
四级听力高分:重在提升逻辑分析和思维能力
四级考试听力短对话同义替换总结(中)
四级考试听力为英语专业四级旧题
英语四六级听力冲刺之克服误区掌握技巧
大学英语四级听力考试冲刺辅导
四级考试听力理解短对话原文
大学四级必过两大支柱之听力理解复习指导
名师点评四级听力:重视技巧 把握关键词
英语听力备考讲义与笔记(三)
四级考试完整答案
大学英语四级考试听力高分技巧
英语四级考试听力训练方法
英语四级考试听力必背词汇短语
英语四级听力辅导之充分利用听力材料
英语听力备考讲义与笔记(五)
听力理解复合式听写原文
英语四级听力猜题技巧
英语真题听力11-18题短对话
英语四级复合式听写原文
大学四级听力考试“猜”题技巧
四级考前30天:听力重点场景必背词汇
大学英语四级听力长对话通关秘笈
大学英语四级听力考试常见词汇
不限 |
英语教案 |
英语课件 |
英语试题 |
不限 |
不限 |
上册 |
下册 |
不限 |