VIENTIANE, May 23 -- As each row of 14 cement sleepers laid smoothly across the Ban Nong Khay Tunnel at the prescribed distance and then the 500-meter long tracks settled on the sleepers precisely by the engineering train, China-Laos Railway's tracks has passed its first tunnel on Saturday.
The 661-meter-long Ban Nong Khay Tunnel is located in Vientiane Province, some 60 km to the north of Capital Vientiane, at the juncture of central and northern Laos' plains and mountains.
Lei Chao, secretary of the Communist Party of China (CPC) working committee at the China Railway No. 2 Engineering Group (CREC-2) railing base, which undertakes the track laying of the China-Laos railway, told reporters that amid the COVID-19 pandemic, the CREC-2 has been actively planned the work and mobilized over 700 Laotians and 200 Chinese engineers and workers who cooperated closely and effectively, raising the railing speed from two km per three days at the beginning to 1.5 km daily now.
The track laying work was kicked off on March 27 in Vientiane.
The 414-km railway, with 198-km tunnels and 62-km bridges, will run from Boten border gate in northern Laos, bordering China, to Vientiane with an operating speed of 160 km per hour.
The electrified passenger and cargo railway is built with the full application of Chinese management and technical standards.
The project started in December 2016 and is scheduled to be completed and open to traffic in December 2021.
造就一个美好的生活
KKR亚洲基金完成60亿美元筹资
充实的生活 就是简简单单
源于生活中的哲理
怎样提高我们的自尊
全力以赴
当爱向你招手
在郁闷的日子里
End the Analysis Paralysis
承诺来之不易
美国仍未摆脱财政悬崖危机
美PE公司迫于压力出售造枪企业
《纽约时报》记者签证申请仍在考虑中
丰田和奥迪研发自动驾驶汽车
你的幸福,你的责任
亚洲必须摆脱西方思维的束缚
心中的一道亮丽风景
美国将加强与欧盟经济合作
美国逼近财政悬崖
飘忽的云
怀念恩师
活出你的精彩
彼岸无尽头,知足才常乐
全球最佳CEO百人榜出炉
老板当上父亲未必会更好
卜拉希米特使呼吁成立叙利亚过渡政府
2012年最佳与最差广告创意
四棵细瘦的树
阁楼上的流浪者
握紧我的手
不限 |
英语教案 |
英语课件 |
英语试题 |
不限 |
不限 |
上册 |
下册 |
不限 |