KATHMANDU, Aug. 11 -- Nepal has completed reconstruction of around 40 percent of cultural and archaeological monuments that were damaged in the earthquake of 2017, according to National Reconstruction Authority (NRA).
The latest reconstruction update provided by NRA states that out of total 891 cultural heritages damaged in the disaster, reconstruction of 380 sites including 96 within the world heritage sites and 284 within the other cultural sites has been completed so far.
A total of Rs 2.12 billion (18.66 million U.S. dollars)has been spent on the rebuilding of these damaged monuments in the last over four years.
"We have intensified the reconstruction task of cultural heritages. But it is true that construction has not been in speed pace as compared to other sectors like infrastructures, schools or hospitals," Pitambar Ghimire, joint secretary and NRA spokesperson told Xinhua on Sunday.
Ghimire explained that the reconstruction of heritages sites faces several challenges like maintaining originality of the rich heritage, availability of manpower skilled in art and architecture, availability of traditional construction materials among others.
"Reconstruction of ancient and culturally rich sites requires cooperation from local communities and archaeological experts as well. We have been trying our best to complete the remaining works soon," spokesperson Ghimire added.
In coordination with NRA, Department of Archaeology has been entrusted with the reconstruction of heritage sites, which has to fully comply with archaeological principles like using only traditional bricks and timber to maintain the originality and avoiding modern construction materials among others.
According to Damodar Gautam, Director General at Department of Archaeology, at least 150 heritage sites would be constructed in the current fiscal year, for which budget has already been allocated.
"Since we have around two years left to complete the overall reconstruction process, we are hopeful that the remaining heritage sites will be built on time, Gautam informed Xinhua.
The major heritage sites being reconstructed currently are Kasthamandap and Nine-Storey Tower located in Hanumandhoka Durbar Square, Nine-Storey Dharahara Tower, Machhindranath temple, Ranipokhari or Queen's Pond among others.
Besides the internal resources of the government, the monuments are being reconstructed with the assistance of different countries like China, India, the United States, Japan, Switzerland and Sri Lanka among others. Nine-Storey Tower located inside the UNESCO world heritage site in capital and Seven-Storey Nuwakot Palace in the neighboring district are undergoing reconstruction under China's aid.
According to the Post Disaster Needs Assessment conducted by National Planning Commission, Nepal faced a financial loss of around Rs 806 billion in the earthquake, which is more than one third of the country's GDP.
购物口语必备
[口语]返工忧郁症 back-to-work blues
[口语]处世有方的“社交变色龙”
美国当下最流行的常用习语大全
白领族必备的50句英语潮句
[口语]用地道英语表达“身体好”
趣味翻译:帅又不能当饭吃
[翻译]十句常用的美国俚语
英语课堂教学活动设计——以The Area I l...
英语中名词性从句引导词辨析
“冬至”英语怎么说?
学俚语记单词:古堡惊魂与美女的投怀送抱
容易让英语学习者误入陷阱的妙趣横生的英语单词
《绝世天劫》总统演讲部分 适合英语口语模仿
墨西哥湾“漏油事件”相关词汇
看天气预报必须知道这些英文单词
盘点与“茶”有关的地道英语
6人英语话剧《女人之间的战争》
足球相关英语
6人的英语剧本:出租车司机
外贸常用英语口语100句
如何用英语买到称心好礼
6人英语剧本,一个大学新生的故事,一个女孩的故事
[口语]你有“选择焦虑症”吗?
[口语]与药家鑫案相关的词汇
英语讨薪十板斧
[口语]高考“生源” student pool
你遭遇了“新年障碍”吗
英语小品剧本:魔豆
6人-8人超级搞笑英语话剧剧本《臭脚的故事》
| 不限 |
| 英语教案 |
| 英语课件 |
| 英语试题 |
| 不限 |
| 不限 |
| 上册 |
| 下册 |
| 不限 |